Minnesota Power Arrowhead Regional Emission Abatement (AREA) Plan
The AREA Plan was proposed to regulators by Minnesota Power in October 2005. It called for MP to voluntarily take steps to reduce air emissions at the two of its generating stations closest to the Boundary Waters Canoe Area Wilderness.
Work began with 60-megawatt Unit 2 of the Laskin Energy Center in Hoyt Lakes. During October and November 2006, Foster-Wheeler low-nitrogen oxide (NOx) burners, over-fire air systems and software networks were installed that are expects to reduce NOx emissions by 66 percent.
The retrofits, when combined with Laskin’s existing wet particulate scrubbers’ sulfur dioxide removal capability, are designed to deliver a multi-emission approach to pollutant controls.
Construction costs at Laskin Unit 2 were approximately $3 million.
Installation of essentially the same equipment on Laskin Unit 1 was accomplished for about $2.2 million.
With completion of the Laskin retrofit, work began almost immediately on Taconite Harbor Energy Center’s Unit 2. The project was installation of technology based on a Swedish researcher’s findings that modifying the combustion process is the most effective and lowest-cost method of emissions control.
Minnesota Power contracted with MobotecUSA, a California firm, to custom-design a control system for Taconite Harbor Unit 2. Ductwork was installed to allow injections of various sorbents into the process at key points to control sulfur dioxide, NOx and mercury. Although Mobotec’s process is marketed as a means of controlling the oxides, at a power plant in Cape Fear, N.C., it also reduced mercury by 89 percent. Minnesota Power anticipates the system will cut NOx emissions by more than 60 percent and sulfur dioxide emissions by 65 percent.
Work is expected to be completed by this spring.
AREA Frequently Asked Questions
top |